• May 2022 Construction Update

    Posted by Clay Walker on 5/16/2022

    Link to the May 2022 Construction Update (includes pictures)

    • PIER DRILLING FOR THE FOUNDATION IS IN PROGRESS
    • BEAM EXCAVATION IS IN PROGRESS.
    • LIFT STATION CASING IS COMPLETE.
    • RCP INSTALLATION FOR THE STORM SEWERS ARE COMPLETE.
    • BUILDING PAD INSTALLATION IS NEARING
      COMPLETION.
    • POSTS FOR THE ELECTRICAL PANELS HAVE BEEN ESTABLISHED.

     

    Cost Summary

    cost summary

    Comments (-1)
  • February 18, 2022 Update

    Posted by Sheri Payne on 2/18/2022
    Update 2-18-22
     
    Intermediate Campus:
    The design and bid phase is complete, and the board voted on February 17 to approve the total cost and contractors for the construction phase to begin.   As we have reported previously, the LRPC agreed to add square footage to the new campus so we don't open it at capacity.  This gives us room to grow into it.  Adding square feet comes at a cost, but we were able to get it in at $24,228,401, which is less than the approved $25 million.  This is a blessing given the current economic climate.  The remaining funds have been used to address other concerns we hoped to accomplish with this bond.  They include:
    -Repaired JH and Rock gym parking area
    -Improved parent traffic flow at the JH
    -Resolved drainage issues at the JH parking area
    -Replaced HVAC in the elementary cafeteria
    -Upgrade technology infrastructure needs on campuses 
    There has been a lot of time and energy spent to get to the point of breaking ground, but spending the appropriate amount of time on design and bidding will save us time in the long run.  We know people are eager to see dirt turning, and we are finally moving into the construction phase!  We are on schedule, as planned, to turn dirt in March.  Thank you for your patience.  As always, we will strive to be transparent and fiscally responsible with our taxpayers money.  Feel free to reach out to us anytime you have a question.   
     
    Multi-purpose field house:
    The slab is poured and the structure is going up!  We estimate it will take 3-4 weeks for the building to be erected.  At that time, we will begin installing rough-in items.  
    Comments (-1)
  • Update 12-10-21:

    Posted by Webmaster on 12/10/2021
    Intermediate Campus:
    First, let me apologize for not getting this on our website sooner.  As many of you know, there is lots of planning that takes place in order to break ground on a 70,000 square foot new campus.  Although dirt has not started to turn, there have been lots of meetings and work being done behind the scenes to ensure we are providing the best facility we can and being fiscally responsible to our community.  Besides building out construction documents, some of that work also includes mechanical, electrical, and plumbing engineering; soil samples; design meetings; and surveys.  One factor that our LRPC (long range planning committee) had to pause and consider was how the unprecedented growth we saw this summer affected the original plan for the new intermediate campus.  Their unified consensus was not to open the campus and be at capacity immediately.  This prompted the administration and architects to work together to grow the footprint of the building by approximately 10,000 square feet to accommodate more students, which means the entirety of the May 2021 bond will need to go toward the new intermediate campus.  I am pleased to announce we are nearing completion of the construction document phase and should be ready to begin bidding out the work in early January.  We are still on track, and shooting for occupation by August 2023.  You can expect to see dirt turning and mobilization of crews by March 2022.  
     
    Here are a few looks at the elevations of the new building.  It will accommodate grades 4-6 and a total student population of 600.  There will be a new cafeteria, library, and gymnasium as planned.   
     
     
    All purpose field house:
    This project has taken longer than expected to get off the ground.  Due to various economic and regional workforce reasons, the district has had a difficult time getting certain trades to show interest in the job.  However, we are finally able to move forward.  Plumbing should start in the next week, and concrete poured in January.  The building package has been delivered, and erection will begin as soon as the foundation is ready.  We are shooting for completion by summer.  It will take some pushing and organization, but we are very hopeful.  
     
    Other:
    As we mentioned before, thanks to you, we were able to address the parking lot, drainage issues, and parent pick up loop at the JH and rock gym with bond proceeds.  This has proven to be a great benefit to that campus and our families.  We also replaced the elementary cafeteria HVAC unit and brought in more portables to accommodate the growth.    
     
    As things develop and change, our goal is to be completely open, honest, and transparent each step of the way.  Building a new school is a lot of work, but it is also fun and exciting.  If you have any questions, don't hesitate to reach out to us. 
     
    With appreciation,
    Lance Johnson
    Superintendent
    Peaster ISD         